ROAD AND TRAFFIC INDEX
Lemery, Batangas
LEMERY, BATANGAS
SURVEYED PAVEMENT DISTRESS IN MARASIGAN STREET
Defect(s)/Deficiencies Estimated Quantity Unit of Measure Remarks Length Width Depth No. of Slab Latitude Longitude
Ongoing Rehabilitation Total: 126
On-going Rehabilitation of Pavement 1 13.88636 120.9132
7 13.8858 120.9126
Wornout Surface 55.8 sq. m 2 13.86953 120.9131
Distress Inlet 2.4 sq. m 2m 1.2 m 7 13.8858 120.9126
corner cracking 0.5 l.m 0.5 m 2 cm 1.2 cm 8 13.88571 120.9122
23 13.88539 120.9116
Filipinismo St/Co 34 13.88497 120.9111
Transverse Crack 2 l.m 3m 50mm 1.4 cm 39 13.88638 120.9133
Transverse Crack 2 l.m 3m 50mm 2 cm 45 13.88476 120.9107
Sangalang St/Co 48 13.88467 120.9106
Pothole 0.32 sq. m 1m 32cm 1 cm 49 13.88549 120.9121
Pothole (Delamination) 0.195 sq. m 50 cm 39 cm 1.3 cm 53 13.88451 120.9106
End Wornout surface 251.1 sq. m 58 13.88597 120.911
Rehabilitated Pavement/SE 59 13.88597 120.911
68 13.88425 120.91
Pothole (delamination) 0.1728 sq. m 54 cm 32 cm 9 mm 69 13.88428 120.91
Pumping 27.9 sq. m 82 13.88398 120.9095
Dona Conchita/In 109 13.88342 120.9085
End ng Wornout Surface 474.3 sq. m /E 126 13.88301 120.9079
Note: Legend: /SE - Start to End
1. The data is surveyed last February 17, 2022. /E - End
2. The unit of measure l.m denotes linear meter. /In - Intersection
/Co - Corner